1. This site uses cookies. By continuing to use this site, you are agreeing to our use of cookies. Learn More.
Dismiss Notice
You must be a registered member in order to post messages and view/download attached files in this forum.
Click here to register.

First 9001, after that 10006?

Discussion in 'ISO 9001:2015 - Quality Management Systems' started by Qualmx, Jul 24, 2019.

  1. Qualmx

    Qualmx Well-Known Member

    Joined:
    Oct 7, 2015
    Messages:
    464
    Likes Received:
    59
    Trophy Points:
    27
    Location:
    Mexico
    Hi all
    Could someone share experiences with iso 9001 and 10006?
    To use 10006, it must be implemented first 9001? Or can run alone?
    What are the benefits to use 10006 supported by 9001?
    Is a company managing engineering and construction projects.
    My question is focused in project management activities.
    Thanks
     
  2. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,109
    Likes Received:
    2,562
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    DO you have copies of 10006? You don't necessarily have to have ISO 9001, to ensure the project quality activities are covered. It helps, of course. (I'm not talking of certification btw)
     
  3. Qualmx

    Qualmx Well-Known Member

    Joined:
    Oct 7, 2015
    Messages:
    464
    Likes Received:
    59
    Trophy Points:
    27
    Location:
    Mexico
    Thanks Andy
    At what extent 9001 could improve the 10006 activities?
    What issues or gaps are missing in 10006, that 9001 could complete?
    or what additional benefits it may have an organization by adding 9001?
    Thanks for your guide.
     
  4. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,109
    Likes Received:
    2,562
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    Think of it this way:

    ISO 9001 defines a QMS for a whole organization
    ISO 10006 defines a QMS for a project, usually in a Project Quality Plan.

    Of course, if you know what ISO 9001 is, you'll (should) understand the relevance of a PQP. But the two are mutually exclusive.