How to fix RPN in PFMEA

Discussion in 'FMEA - Failure Modes and Effects Analysis' started by Bheemaraj, Jan 19, 2016.

  1. Bheemaraj

    Bheemaraj New Member

    Joined:
    Jan 19, 2016
    Messages:
    1
    Likes Received:
    0
    Trophy Points:
    1
    In PFMEA as per AIAG how to fix RPN
     
  2. Bev D

    Bev D Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    606
    Likes Received:
    664
    Trophy Points:
    92
    Location:
    Maine
    do you mean how to determine the RPN or how to fix the process to reduce the RPN?
     
  3. tony s

    tony s Well-Known Member

    Joined:
    Sep 10, 2015
    Messages:
    1,350
    Likes Received:
    1,055
    Trophy Points:
    112
    Location:
    Laguna Philippines
    I believe you want to have a "threshold level" for RPN - where actions are determined if the RPN value goes above this threshold level. The 4th Edition of the AIAG Manual for Potential Failure Mode and Effects Analysis specifies that "The use of RPN threshold is NOT a recommended practice for determining the need for actions." See page 57 and 103 of the AIAG Manual.

    If your intention is to reduce the value of the RPN, then actions should be recommended, implemented and evaluated. The following should be considered when taking actions:
    • The primary objective of taking actions is to reduce risks and increase customer satisfaction by improving the product/process design.
    • Assessment for preventive/corrective action should be first directed to critical classification, then high severity, then high RPN, and other items designated by the team.
    • The intent of any action is to reduce rankings in the following order: Severity, Occurrence, and Detection.
    • Only a design revision can bring about a reduction in the Severity ranking.
    • Increasing the frequency of quality inspections is not an effective preventive/corrective action.
    • Identify the person or group for each recommended action and assign target completion date.
     
    Atul Khandekar likes this.