Identify outsourced processes (IATF 8.4.2.1)

Discussion in 'IATF 16949:2016 - Automotive Quality Systems' started by John C. Abnet, Feb 4, 2020.

  1. John C. Abnet

    John C. Abnet Well-Known Member

    Joined:
    May 23, 2017
    Messages:
    710
    Likes Received:
    510
    Trophy Points:
    92
    Location:
    Upper Midwest- USA
    Good day QFO team;
    I'm sure everyone has seen or used various methods to address this requirement. I am curious to hear from everyone regarding a method they have used, seen, or prefer. Thoughts?
     
  2. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,109
    Likes Received:
    2,562
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    I'd suggest that, technically, the correct place for this is embedded in the APQP process - although the AIAG APQP document is woefully lacking on details. It can be handled, by flowing down the relevant parts of the phase requirements pertaining to supplier processes.
     
    John C. Abnet likes this.
  3. John C. Abnet

    John C. Abnet Well-Known Member

    Joined:
    May 23, 2017
    Messages:
    710
    Likes Received:
    510
    Trophy Points:
    92
    Location:
    Upper Midwest- USA
    Agreed @Andy Nichols . Ideally, this would be identified on the control plan since the control resolution for such and identification is at the product level.

    Still curious to have others weigh in to see what they've experienced regarding this .
     
    Andy Nichols likes this.