AS9102 B - Is a FAIR required for a note change which triggers the drawing to be up issued?

Discussion in 'AS 91XX - Aerospace Quality Standards' started by Kapow88, Feb 4, 2020.

  1. Kapow88

    Kapow88 New Member

    Joined:
    Jan 18, 2019
    Messages:
    3
    Likes Received:
    0
    Trophy Points:
    1
    An example, a supplier changes name of an adhesive, everything stays the same apart from the supplier name is changing.
    The drawing references the supplier name so therefore the drawing will change to the new supplier or be removed all together. This change will trigger an up issue in revision to the drawing.
    I believe an FAI is required to comply with configuration control. How else can this be managed and controlled otherwise?
     
  2. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,109
    Likes Received:
    2,562
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    Welcome!

    I always though that drawing should NEVER call out a supplier name (product or provider) because of such issues, but it seems that your organization has chosen to do that. As far as I understand such a note isn't affecting Fit/Form/Function (as long as the adhesive properties haven't changed) so you should be OK without a new first article. Has there been validation of the adhesive? Is it JUST a name change?
     
  3. Kapow88

    Kapow88 New Member

    Joined:
    Jan 18, 2019
    Messages:
    3
    Likes Received:
    0
    Trophy Points:
    1
    It is just a name change, the products material composition has not been affected.
    These are legacy drawings which call up the supplier name in the BOM. The BOM is referenced on the drawing.