5.1.1.3 and 5.3 Organizational Roles and Responsibilities and Process Owners

Discussion in 'IATF 16949:2016 - Automotive Quality Systems' started by MCW8888, Feb 17, 2017.

  1. MCW8888

    MCW8888 Well-Known Member

    Joined:
    Aug 17, 2015
    Messages:
    642
    Likes Received:
    198
    Trophy Points:
    42
    I am doing an IATF 16949 gap analysis using the AIAG tool and the Quality Manual and also the standards. In the manual the process owners are defined in the roles and responsibilities. Will I have a problem during an external audit if there is no separate paragraph to describe process owners? Thanks.
     
  2. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,104
    Likes Received:
    2,560
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    Good question! What were you thinking would be in the "separate paragraph"?
     
  3. MCW8888

    MCW8888 Well-Known Member

    Joined:
    Aug 17, 2015
    Messages:
    642
    Likes Received:
    198
    Trophy Points:
    42
    Do I have to have a section titled Process Owners. I did not changed this section of the manual. But the standard had a separate requirement for process owners. Our SOP's also describe roles and responsibilities. Thanks.
     
  4. Andy Nichols

    Andy Nichols Moderator Staff Member

    Joined:
    Jul 30, 2015
    Messages:
    5,104
    Likes Received:
    2,560
    Trophy Points:
    112
    Location:
    In the "Rust Belt"
    Sounds like a matrix added to the manual which relates the specific clause, to where else you covered process ownership would be fine...
     
    Last edited: Mar 11, 2017
    MCW8888 likes this.
  5. MCW8888

    MCW8888 Well-Known Member

    Joined:
    Aug 17, 2015
    Messages:
    642
    Likes Received:
    198
    Trophy Points:
    42
    I just did a RACI matrix.
     
  6. rajesh

    rajesh New Member

    Joined:
    Nov 14, 2016
    Messages:
    1
    Likes Received:
    0
    Trophy Points:
    1
    what is RACI matrix. please share it
     
  7. MCW8888

    MCW8888 Well-Known Member

    Joined:
    Aug 17, 2015
    Messages:
    642
    Likes Received:
    198
    Trophy Points:
    42
    The RACI Matrix is a powerful tool to assist in the identification of roles and assigning of cross-functional responsibilities to a project deliverable or activity
    RACI represents: R - Responsible, A - Accountable, C - Consulted, and I - Informed
    RACI Definitions:
    Responsible
    = The person who executes the work and makes sure the task objective is achieved. There is only one person assigned as the Responsible role, although others can be delegated to assist.
    Accountable = The person who is answerable for the correct and thorough completion of the deliverable or task, oversees and approves the Responsible tasks and deliverables. There must be only one Accountable party specified for each task or deliverable
    Consulted = The person(s) whose opinions are sought, typically subject matter experts; and with whom there is two-way communication
    Informed = Those who are kept up-to-date on progress, often only on completion of the task or deliverable; and with whom there is just one-way communication

    I might have seen a simple matrix in this forum. We have a complex one for the R&D division, It's a confidential document with names written on it. Hope this helps a bit.
     
    Atul Khandekar likes this.
  8. charanjit singh

    charanjit singh Member

    Joined:
    Jan 21, 2016
    Messages:
    32
    Likes Received:
    10
    Trophy Points:
    7
    For a number of years, I have used Matrix of Responsibility for various processes, using the following abbreviations:

    P = Primary Responsibility of...
    S = Secondary Responsibility or Support to be provided by...
    I = Information to be given to...
    C = Coordination by (this was rarely used)

    No CB auditor ever commented on this.
     
  9. johnnymo77

    johnnymo77 Active Member

    Joined:
    Sep 1, 2015
    Messages:
    51
    Likes Received:
    16
    Trophy Points:
    7
    Location:
    Niles Michigan
    Here's our APQP RASIC as an example.
     