    What is the difference between APQP and contract review? They seem to overlap quite a bit.
     
  2. Nikki

    Nikki Well-Known Member

    Joined:
    Jul 31, 2015
    Messages:
    268
    Likes Received:
    141
    Trophy Points:
    42
    Location:
    Maine
    As far as I could see, APQP is creating the processes needed to make a particular product, more than likely for the automotive industry. Contract review is geared more towards what the customer wants and requires, customer specifications, purchase orders, etc.
     
    Michael likes this.
  3. Emmyd

    Emmyd Member

    Joined:
    Jul 31, 2015
    Messages:
    38
    Likes Received:
    38
    Trophy Points:
    17
    Location:
    Tennessee
    Contract review should be done during APQP to ensure that the customer's expectations and specifications are part of the planning process. Part of APQP is to review those specs and requirements, in addition to production planning, design considerations, etc. APQP encompasses anything that plays any kind of role in producing a part for a customer.
    Hope this helps!
     
  4. Celeste

    Celeste Member

    Joined:
    Aug 10, 2015
    Messages:
    9
    Likes Received:
    0
    Trophy Points:
    1
    That is what I think as well. From your experience, are all the chapters (phases) of APQP done prior to the RFQ or just phase 1 and 2.
     
  5. Emmyd

    Emmyd Member

    Joined:
    Jul 31, 2015
    Messages:
    38
    Likes Received:
    38
    Trophy Points:
    17
    Location:
    Tennessee
    Mostly, what we do as a part of the RFQ process is a feasibility analysis and making sure we have all the relevant information to make an effective analysis. The remaining phases we do after we are awarded the part(s). A lot of what is done during the RFQ process depends on your customer's requirements.
     
    Tom Waite and Bazinga like this.
  6. Tom Waite

    Tom Waite Member

    Joined:
    Aug 3, 2015
    Messages:
    45
    Likes Received:
    33
    Trophy Points:
    17
    Location:
    Grand Rapids Michigan Area
    I would like to think this is how most companies operate, and in fact, many companies will recognize their core business processes and have generic quality plans as baseline starters for customer specific plans. That way when the RFQ and feasibility are completed, it could be matched up to a generic baseline process and expanded on from there as needed. APQP could be as simple as the customer wants you to preform a core process to your business with the expected outcomes predetermined. Standard service vs. Customer Specific service. Don't re-create the wheel every time if you do not have to.
     
    Michael likes this.
  7. Michael

    Michael New Member

    Joined:
    Sep 4, 2015
    Messages:
    3
    Likes Received:
    3
    Trophy Points:
    2
    Location:
    China
    Normally, after finishing contract review and approved by management, we start the APQP
     
  8. Scott

    Scott Member

    Joined:
    Sep 1, 2015
    Messages:
    16
    Likes Received:
    9
    Trophy Points:
    2
    Location:
    UK
    From my experience contract review would be carried out first - once you have established what the customer requires and feasibility of this, the APQP process would then take over throughout the product lifecycle from development through to production.

    You can then tie in the design reviews or stage gates to the contract reviews and feedback to the customer - i found this part to be particularly important when changes are required and ensuring approval from all parties was established before moving onto the next element

    Contract review is more of a process step where as APQP is for want of a better explanation, a framework